yep, it's green
this stuff is for the green deck
new FP flue pieces solved the install puzzle.
flue heading towards the roof penetration
next week looks like another busy one. we should have retaining walls started for the back side of the house. steel fabricator should start on the permanent stairs. temporary stairs come down tomorrow since the foam guys need to get more scaffolding to reach the top parts of the tower. we are also expecting holes to be drilled for the geothermal hvac. all that and we hope drywall will start by end of next week.